Featured EPC Project • Engineering Case Study

Suntory PepsiCo Vietnam Beverage Plant NH3 Refrigeration Project

Tan Long engineered, supplied, and commissioned the high-capacity industrial NH3 refrigeration system for Suntory PepsiCo Vietnam at their Dong Nai manufacturing facility. Delivering 2 heavy-duty cooling modules, the installation satisfies demanding thermal velocity standards for beverage syrup blending and pre-carbonation cooling.

Project Dossier: Suntory PepsiCo Vietnam Beverage Plant NH3 Refrigeration Project represents a turnkey EPC industrial refrigeration achievement delivered by Tan Long Refrigeration & Electrical Engineering JSC. Encompassing thermodynamic modeling, in-house pressure equipment manufacturing, and complete on-site commissioning, the facility meets strict global food safety codes (HACCP, ISO 22000, FDA) with an engineered lifespan exceeding 25 years.
Client / Investor: Suntory PepsiCo Vietnam Beverage Co., Ltd.
Facility Location: PepsiCo Beverage Plant, Dong Nai Province
Scale & Capacity: Industrial NH3 Chiller plant for carbonated soft drink processing lines
Design Temperature: +1°C to +4°C (CO2 saturation chilled process water)
Key Engineering Highlight: Shell-and-tube NH3 chillers built with food-grade stainless steel circuits provide continuous 1°C process water optimizing carbonation solubility for brands such as Pepsi, 7Up, and Mirinda.

1. Client Objectives & Stringent Technical Requirements

For the Suntory PepsiCo Vietnam Beverage Co., Ltd. facility, uninterrupted cold chain integrity demands continuous 24/7 thermodynamic stability. Key design criteria addressed by Tan Long's engineering teams include:

  • Pinpoint Thermal Stability: Operating within +1°C to +4°C (CO2 saturation chilled process water) with strict temperature tolerances within ±0.5°C to prevent product shrinkage or crystallization.
  • Energy Efficiency Optimization: Deploying variable-frequency screw compressors coupled with smart floating head pressure control to curb peak-hour power tariffs.
  • Zero Compromise on Refrigerant Safety: Utilizing Industrial NH3 (R717) paired with automatic shut-off valve manifolds and multi-point ammonia leak detection.
  • Long-Term Structural Durability (25+ Years): High-density flame-retardant sandwich panels and floor frost-heave mitigation systems withstanding heavy forklift traffic.

2. Advanced Thermodynamic Solutions Delivered by Tan Long

To fulfill these rigorous expectations, Tan Long deployed an integrated thermodynamic architecture:

  • Centralized Compressor Stations: High-efficiency Japanese/German industrial screw compressors equipped with stepless slide-valve capacity modulation.
  • In-House Fabricated Pressure Vessels: High-pressure liquid receivers, surge drums, and oil separators built at Tan Long's manufacturing plant under ASME and TCVN standards.
  • Induced-Draft Evaporative Condensers: Closed-circuit cooling towers cutting water consumption by over 30% compared to traditional open cooling towers.
  • SCADA IoT Automation: High-speed PLC controllers transmitting real-time thermodynamic metrics to control rooms and mobile devices with automatic anomaly alerts.

3. Equipment Bill of Materials & Technical Specifications

Summary of core refrigeration equipment engineered, manufactured, and commissioned for Suntory PepsiCo Vietnam Beverage Co., Ltd.:

Equipment Category Technical Specification Quantity / Scope Origin / Fabrication
Compressor Packages Multi-stage industrial screw compressor racks with inverter control 01 Main Station Imported (Japan / Germany)
Evaporative Condensers Induced-draft evaporative condenser with anti-corrosive alloy casing 01 - 02 Units Imported specialized OEM
Pressure Vessels & Surge Drums ASME / TCVN certified high-pressure receiver & liquid overfeed vessels Complete Module Fabricated by Tan Long
Insulated Cleanroom Envelope High-density PIR/PU sandwich panels with camlock fasteners Entire Facility Fabricated by Tan Long
Automation & Control System Central PLC SCADA with remote temperature monitoring & alerts 01 Console Rack Siemens / Schneider / Tan Long

4. Operational Metrics & Client Performance Validation

Following comprehensive load testing and thermodynamic commissioning, the plant was officially handed over for commercial operation. Measured performance metrics confirm:

-25%
Reduction in utility power bills achieved through VFD staging and heat reclaim.
±0.3°C
Chamber temperature uniformity confirmed across all sensors via SCADA.
100%
Passed all statutory hygiene, structural, and mechanical safety inspections.

The client's project management and operations team expressed complete satisfaction with Tan Long's turnkey execution capability, disciplined job-site safety, and dedicated 24/7 technical lifecycle support.

Technical Project FAQs

1. What role does refrigeration play in soft drink bottling?

Lower water temperature (1-4°C) dramatically increases CO2 absorption efficiency and beverage carbonation stability. Tan Long's chillers maintain uniform fizz quality.

2. What engineering standards were audited by Suntory PepsiCo?

The project cleared stringent global compliance audits mandated by both Suntory (Japan) and PepsiCo (USA) regarding thermodynamic efficiency and environmental safety.

NEED A TURNKEY EPC INDUSTRIAL COLD STORAGE SOLUTION?

Tan Long provides turnkey EPC services: Heat load analysis - Genuine equipment procurement - ISO/HACCP certified installation - 24/7 preventive maintenance. Guaranteed 25% - 30% operating power savings.

Calculate Heat Load & Capacity Equipment & Turnkey Pricing Book On-Site Engineering Survey

TECHNICAL EXPERT VERIFICATION

Updated: September 2026 • Standards: TCVN 6739 & QCVN 06:2022
Eng. Nguyen Van Long - EPC Technical Director
EXPERT AUTHOR

Eng. Nguyen Van Long

EPC Technical Director & Head of Refrigeration Solutions, Tan Long

20+ years EPC experience in industrial cold storage systems, IQF quick freezers, and automated ASRS facilities. Thermal Engineering alumnus from HCMC University of Technology, VISRAE Executive Board member.

M.Sc. Tran Dinh Hung - Pressure Safety Lead, Tan Long
TECHNICAL VERIFICATION

M.Sc. Tran Dinh Hung

Pressure Vessel Safety Verification & Energy Auditing Lead

15+ years leading NH3 piping pressure safety proofing, COP energy audits, and fire protection certification for PIR/PU panel enclosures under QCVN 06:2022/BXD.